When Dispute Resolution Becomes the Dispute: A Commercial Lesson for Caribbean Construction Projects
Construction contracts generally contain detailed provisions governing how disputes are to be resolved. Considerable attention may be devoted during negotiations to selecting the appropriate dispute resolution mechanisms, including dispute boards and arbitration. Once the contract is signed, the same attention is not always given to the practical arrangements needed to ensure those mechanisms operate effectively.
This is particularly important where the contract provides for a dispute board. Across the Caribbean, parties may agree to establish a board but fail to appoint its members or make the arrangements necessary for it to function. With attention focused on mobilising resources and commencing the works, the appointment of the board is easily deferred. The consequences become apparent when a dispute arises, and the parties discover that the very mechanism they agreed upon to manage their disagreements is not in place. By that stage, the parties may find themselves disputing not only the substantive issues arising from the project, but also the procedure by which those issues should be resolved.
Two decisions from Trinidad and Tobago illustrate how parties can incur additional time and expense resolving disagreements over the applicable dispute resolution procedure, before the underlying dispute is even addressed.
When the Agreed Dispute Board Is Never Appointed
In Quantum Construction Limited v Newgate Enterprises Co. Ltd (2014), the parties entered into a construction contract incorporating the FIDIC 1999 Conditions of Contract. They agreed to a dispute resolution procedure involving a Dispute Adjudication Board (DAB), followed by arbitration where necessary. Despite this agreement, the parties never took the steps necessary to appoint the board and proceeded with the contract in its absence.
When a payment dispute arose, the contractor commenced proceedings in the High Court of Trinidad and Tobago seeking approximately TT$1.8 million for work performed and services rendered. Rather than addressing the underlying claim, the parties found themselves in litigation over the appropriate dispute resolution procedure. The contractor maintained that arbitration was not mandatory because no DAB had been appointed, while the employer argued that the dispute should be referred to arbitration in accordance with the contract. The Court agreed with the employer, finding that the contractual provisions expressly allowed disputes to proceed directly to arbitration where no DAB was in place, including where a board had never been appointed. It therefore stayed the court proceedings, requiring the parties to pursue the resolution of their dispute through arbitration.
The failure to appoint the DAB left the parties without an established board to which they could refer their payment dispute. Instead, they became embroiled in court proceedings over the applicable dispute resolution procedure, incurring additional costs and delays without making progress towards resolving the payment claim. The mechanism they had agreed upon to assist with the resolution of disputes was unavailable when it was needed.
For construction projects, the implications go beyond the cost of litigation. A standing dispute board appointed at the outset can follow the progress of the works, develop an understanding of the project and intervene, where authorised, before disagreements escalate. It also provides the parties with an established means of obtaining decisions while construction continues. Delaying its appointment risks losing those advantages at precisely the time when unresolved disputes can affect cash flow, working relationships and project delivery. While the Court in Quantum Construction ultimately directed the parties towards arbitration, the proceedings illustrate the additional time and expense that can arise when an agreed dispute resolution mechanism has not been put in place.
When the Contract Provides Conflicting Directions
A different problem arose in Ridgewood Shopping Plaza (1979) Limited v Steel Structures Limited (2024), involving the construction of a shopping plaza in Arima, Trinidad. The parties had entered into a construction contract containing conflicting dispute resolution provisions. The Articles of Agreement provided for arbitration, while the Particular Conditions provided for disputes to be referred to a Dispute Adjudication Board (DAB). When the contract was subsequently terminated, this inconsistency became a source of disagreement. The employer sought the appointment of an arbitrator, while the contractor insisted that the dispute should first be referred to a DAB. The matter came before the High Court, which determined that the arbitration provision in the Articles of Agreement took precedence over the DAB provision in the Particular Conditions. The Court accordingly appointed an arbitrator.
The difficulty could have been avoided had the parties ensured that their dispute resolution provisions were consistent before signing the contract. Instead, the inconsistency only came to light when a dispute arose, leaving the parties to incur the time and expense of court proceedings to determine which procedure applied.
The case highlights the importance of reviewing construction contracts as a whole, particularly where standard-form provisions are amended or supplemented by Particular Conditions. Employers and contractors need to ensure that these amendments work alongside the other contractual provisions and do not create conflicting obligations. In Ridgewood, the failure to do so meant that the parties had to resolve a dispute about their contract’s dispute resolution procedure before they could turn their attention to the underlying dispute.
Making Dispute Resolution Work in Practice
The lessons from these cases are particularly relevant to employers and contractors undertaking construction and infrastructure projects in the Caribbean. The effectiveness of a dispute resolution mechanism depends not only on what the parties agree in their contract, but also on the attention they give to making those arrangements work in practice.
During contract negotiations, the parties should consider how their chosen dispute resolution procedures will operate if a disagreement arises. Where standard-form contracts are amended, they should ensure that the amendments are consistent with the other contractual provisions. If a dispute board is contemplated, the contract should clearly establish when and how it will be appointed, its role during construction and its relationship with arbitration.
Once the contract is signed, these arrangements should not be overlooked in the rush to commence the works. The appointment of an agreed standing dispute board should be treated as part of the initial project arrangements, and those responsible for administering the contract should understand when and how the board may be called upon. The parties should also ensure that the board remains properly constituted throughout the project.
These are relatively straightforward measures, but overlooking them can have significant commercial consequences. As Quantum Construction and Ridgewood demonstrate, the cost of failing to address dispute resolution arrangements at the appropriate time may only become apparent when the parties are already in dispute and must spend further time and money establishing how that dispute should be resolved.